Cables installed and run from main control room to power the pumps
Bagging area complete
Progress at smelter
fencing complete
fencing complete
Progress at smelter
100 Metric Tons from Tivani to Mini-plant
100 Metric Tons from Tivani to Mini-plant
Ore processing plant (this handles 1-2k ROM per month, pilot plant. The bigger plant will be 30k ROM per month (30x more productive)